Lead Times & Shipping Custom Metal Parts to New Zealand and Australia

Lead time for custom metal parts depends on process, tooling, sample approval, and freight mode — not on marketing promises. Partform quotes realistic production and shipping windows when you submit a drawing with quantity and destination.

Typical production lead times (indicative)

Process Prototype / first lot Repeat production
CNC machining 2–4 weeks 2–3 weeks
Sheet metal / stamping (with tooling) 4–8 weeks incl. tooling 2–4 weeks
Sand / investment casting 4–6 weeks 3–5 weeks
Closed-die forging (with dies) 6–10 weeks incl. dies 3–5 weeks
Die casting (with dies) 6–12 weeks incl. dies 3–4 weeks

Times vary by complexity, holiday schedules, and inspection requirements. Confirm on quote.

What adds time

  • New tooling or pattern making
  • First-article inspection and buyer approval
  • Special material procurement
  • Surface finishing or assembly steps
  • Peak season at partner facilities

Shipping to New Zealand and Australia

Freight mode (air vs sea), incoterms, and customs clearance affect total elapsed time. Provide your destination city and required arrival date in the RFQ so quotes can include a realistic delivery plan.

How to shorten cycles

Send complete drawings upfront, freeze revision before tooling, and approve samples promptly when required. Use the drawing checklist before submitting.